Trunk Roads - Taunton M5 J25 Case
|
|
| Date: |
Tuesday 26th March 2002 |
| Aggregate: |
Wainwright Moonshill Quarry 6mm
washed |
| Emulsion: |
Nynas JP 200 Polymer Modified |
| Air Temp: |
Min 3°C Max 12°C |
|
Precipitation: |
0 mm |
| Break
Time: |
6 minutes |
| Traffic
Volume: |
Approx 15,000 per day |
|
|
|
|
High Stress Location

Repairs three years old and still
performing |
 |

|
|
Repairs carried out 5 times faster
than conventional means
|
Summary
- Concrete road built in
1976.
- Present day traffic
volumes far exceed predicted traffic volumes.
- Works carried out in 2002
to bond deteriorating joints between Concrete surface and Asphalt surfaces.
- Repairs still there in
2005
- Jetpatcher used as a rapid
repair to a very busy junction.
Benefits
- Jetpatcher repairs were
carried out in a fraction of the time compared with conventional methods.
- Less risk to Road Gang.
- Less traffic delays to
Road Users.
- Long term solution.
- Large Cost Saving.
|
|