  Case study
Jet Repair ProcessMaterialsProducts & ServicesPhoto GalleryVideosCase Studies
Customer's References
 

 
 

Cheshire A41 Case

 
Date: Thursday 22nd April 2004
Aggregate: Tarmac Barrasford Quarry 6mm washed
Emulsion: Colas Patchmaster 200 Polymer Modified
Air Temp: 12°C
Mix Time: 20 seconds
Break Time: 4 minutes
Traffic Volume: 20 per minute
HGV Volume: 12 per minute
 
HGV Traffic Volume 17,000 a day

Repairs 1 year old as of April 2005

Repairs up to 50mm deep

Repairs carried out five times faster than conventional means

 

Summary
  • Potholes and Crazing appearing in Carriageway to depth of up to 50mm.
  • Several potholed areas had been filled with conventional material giving the are a ‘patchwork quilt’ look.
  • Jetpatcher used to seal and fill potholed and crazed areas to prevent further deterioration.

Benefits

  • Repairs were carried out under mobile closure instead of lane closure.
  • Jetpatcher repairs were carried out in a fraction of the time compared with conventional methods.
  • Workmen exposed to less traffic hazards.
  • The repairs are performing substantially better than conventional materials.
    Large Cost Saving.
     